Bihar Awards 500 MWh BESS Project To Six Firms At ₹4.44 Lakh/MW/Month

Highlights :

  • BSPGCL issued the tender for this project in March and awarded the project within three months
Bihar Awards 500 MWh BESS Project To Six Firms At ₹4.44 Lakh/MW/Month Bihar Awards 500 MWh BESS Project To Six Firms At ₹4.44 Lakh/MW/Month

The Bihar State Power Generation Company Ltd (BSPGCL) has awarded its 125 MW/500 MWh battery energy storage system (BESS) project to six bidders. BSPGCL issued the tender for this project in March, awarded the project within three months.

According to the tender results, Barbrik Projects, Saatvik Green Energy, Kundan Green Energy, Prostarm Info Systems, Hindustan Thermal Project (Hindustan Power), and Suryam International emerged as winning bidders for Bihar’s BESS project. All the bidders secured the BESS project at a ₹4.44Lakh/MW/Month tariff.

According to BSPGCL’s BESS tender results, “Barbrik Projects received the largest share with a 37.5 MW/150 MWh capacity, followed by Hindustan Thermal Project and Prostarm Info Systems with 30 MW/120 MWh each. Whereas, Suryam International and Kundan Green Energy were awarded 10 MW/40 MWh each, while Saatvik Green won 7.5 MW/30 MWh.” Under the viability gap funding (VGF) clause of the tender, the selected bidders will also receive up to ₹2.7 million/MWh or 30% of the project’s whichever is lower as the capital cost.

Prostarm will earn an annual rental of ₹15.98 crore for its 30 MW/120 MWh capacity. The company said it would install storage units across multiple grid substations, which would be operated by Bihar State Power Transmission Company Ltd (BSPTCL). On the other hand, Hindustan Power, promoted by Ratul Puri, will develop its share of the project, with installations planned at Bhagalpur (40 MWh), Udakishanganj (40 MWh), and Sitamarhi (40 MWh).

Winners Of Bihar 125 MW/500MWh BESS Tender 

 

Company Name Capacity Awarded (MW) Tariff (lakh/MW/month)
Barbrik Projects 37.5 MW/150 MWh Rs. 4.44
Hindustan Thermal Project 30 MW/120 MWh Rs. 4.44
Prostarm Info Systems 30 MW/120 MWh Rs. 4.44
Suryam International 10 MW/40 MWh Rs. 4.44
Kundan Green Energy 10 MW/40 MWh Rs. 4.44
Saatvik Green 7.5 MW/30 MWh Rs. 4.44

Previous BESS Tender: A Brief Comparison

Based on the tender results, Bihar’s BESS tender was awarded at a higher tariff than NHPC’s 500 MW/1,000 MWh BESS tender in Andhra Pradesh (Tranche II), where projects were awarded to ACME Solar and Patel Infrastructure. ACME Solar secured a 225 MW/450 MWh system near the Ghani substation at ₹2.22 lakh/MW/month, and a 50 MW/100 MWh system near the Kuppam substation at ₹2.10 lakh/MW/month. Patel Infrastructure was awarded a 225 MW/450 MWh project at ₹2.08 lakh/MW/month near the Jammalamadugu substation. However, Bihar’s latest BESS tender tariff matches that of the Solar Energy Corporation of India (SECI), which awarded JSW Energy a 125 MW/500 MWh standalone BESS project at ₹4.41 lakh/MW/month.