World’s Largest Solar Thermal Project Starts Grid Supplies In Dubai

Highlights :

  • The project by Shanghai Electric is the largest solar thermal project in the world in terms of installed capacity, investment size, and molten salt reserve heat
  • It is the largest standalone solar PV project in the world, with an area of 44 square kilometers
World’s Largest Solar Thermal Project Starts Grid Supplies In Dubai

On November 29 (Dubai Time), the Trough Unit No. 1 facility of Shanghai Electric’s 700MW solar thermal and 250MW photovoltaic solar power plant in Dubai has successfully achieved grid-connected electricity generation, marking a significant milestone along the path of the firm’s entry into the renewable energy sector.

The project, for which Shanghai Electric Group is the contractor, is the fourth phase of the solar thermal and PV power plant developed by Dubai Electricity and Water Authority in Mohammed bin Rashid Al Maktoum (MBR) Solar Park. Built on tower and leveraging trough solar thermal power generation technologies, the project overcomes the limitation that conventional PV power stations cannot generate electricity at night, serving as a strong demonstration for Solar Thermal capabilities at a time Solar PV has overtaken it comprehensively.

The 250MW PV modules are dispersed in unused locations to maximize site use, while the 700MW solar thermal facility consists of three 200MW trough units and a 100MW tower unit. It is the largest standalone solar PV project in the world, with an area of 44 square kilometers (approx. 17 sq. miles), the equivalent of just over 6,000 standard soccer fields. The project utilizes roughly 560,000 tons of molten salt and 70,000 heliostats each measuring roughly 25 square meters. The earthwork required for site leveling in the desert amounted to some 40 million cubic meters. The facility, which rises to a height of 262 meters (approx. 860 feet), is the tallest tower solar thermal project in the world. Additionally, it provides the world’s biggest commercially operating slot opening technology with an opening distance of 8.2 meters. Operation of the facility can replace the burning of 2 million tons of standard coal annually. .

Its location in the middle of the desert, where daytime temperatures can soar to close to 50°C (122°F), combined with the impact of the pandemic, among other factors, led to the project encountering several difficulties during construction, including rising costs across-the-board (of which costs for raw materials witnessed the steepest increases), delays in shipping, supply chain challenges to the fabrication of equipment and a severe staffing shortage. By adopting creative solutions and being meticulous in advance preparation, the project department overcame several technical issues to achieve this milestone.

The energy stored in the trough units and the tower unit, once all units are operational, can generate power continuously for a maximum of 13.5 hours at night and 15 hours during periods of inclement weather. When the entire project is completed, it will bring Dubai significantly closer to achieving its 2050 Clean Energy goal of supplying clean power to 320,000 local families and reducing carbon emissions by 1.6 million tons annually.

Largest Solar Thermal Project in the world at Dubai