NTPC Green Energy has commissioned the first 110.25 MW of its planned 1,255 MW Khavda-I Solar Project. The project is being developed by NTPC Renewable Energy Limited, a subsidiary of NTPC Green, and marks a step toward the company’s target of achieving 60 GW of renewable energy capacity.
NTPC Green's latest commissioning aligns with its roadmap for the year ahead, which it shared on an investor call. T he company said, “In renewables, we are expecting an addition of 699 MW. So, in stand-alone, it would be 2,019 MW. In JVs and subsidiaries, it will be a total of 9,787 MW. n JVs and subsidiaries, it will be a total of 9,787 MW. And renewables will be around 6,527 MW. So, all this put together would be 9,787 MW of JV subsidiary capacity. NTPC Group as a whole would tally to 11,806 MW." The company while sharing its projections mentioned, that in renewables it’s expecting an addition of 699 MW.
Sharing details about the factors affecting capacity delays in Khavda and Bhadla, the management said, "Last year, the major slippages were primarily at our Khavda and Bhadla. Khavda, we had planned for a capacity of 1,255 MW. But this got delayed primarily because of the pooling substation getting delayed a little bit, which got commissioned now lately in April, and we are going to start bringing the capacities of Khavda this year. We are planning in the Q1 itself around 600 MW."
NTPC Green Previous Projects
Earlier this year, NTPC Renewable Energy Limited (NTPC REL) , a wholly owned subsidiary of NTPC Green Energy Limited, declared the commercial operation of its 150 MW Gujarat Solar PV Project with the commissioning of its final 60 MW capacity, marking the full commissioning of the project in Limbdi, Gujarat. This solar venture was awarded under the GUVNL 500 MW Solar (Phase XII) tender.
The last segment of 60 MW commenced commercial operation on April 16, 2025. This follows the earlier commissioning of the first 60 MW on July 29, 2024, and the second 30 MW on December 11, 2024. With this milestone, the entire 150 MW capacity of the Gujarat Solar PV Project is now operational.