Canadian Solar Reports Third Quarter 2016 Results

Canadian Solar Reports Third Quarter 2016 Results

canadian solar logo

Canadian Solar Inc., one of the world’s largest solar power companies, announced its financial results for the third quarter ended September 30, 2016.

Third Quarter 2016 Highlights

  • Total solar module shipments were 1,185 MW, of which 1,161 MW was recognized in revenue, compared to 1,290 MW recognized in revenue in the second quarter of 2016, and third quarter guidance in the range of 1,200 MW to 1,300 MW.
  • Net revenue was $657.3 million, compared to $805.9 million in the second quarter of 2016, and third quarter guidance in the range of $660 million to $710 million.
  • Net revenue from the total solutions business as a percentage of total net revenue was 10.4%, compared to 8.5% in the second quarter of 2016.
  • Gross margin was 17.8%, compared to 17.2% in the second quarter of 2016, and third quarter guidance in the range of 14.0% to 16.0%.
  • Net income attributable to Canadian Solar was $15.6 million, or $0.27 per diluted share, compared to $40.4 million, or $0.68 per diluted share, in the second quarter of 2016.
  • Cash, cash equivalents and restricted cash balances at the end of the quarter totaled $986.0 million, compared to $1.0 billion at the end of the second quarter of 2016.
  • Net cash used in operating activities was approximately $205.7 million, compared to net cash provided by operating activities of $145.2 million in the second quarter of 2016.
  • The Company’s portfolio of operating solar power plants now totals 948 MWp, with an estimated total resale value of approximately $1.4 billion.
  • The Company targets to complete the sale of certain utility-scale solar power plants in Canada and China either by the end of 2016 or early 2017 and has started the sale process of its projects in the U.S. as these projects reaching COD.

Third Quarter 2016 Results

Net revenue in the third quarter of 2016 was $657.3 million, down 18.4% from $805.9 million in the second quarter of 2016 and 22.7% from $849.8 million in the third quarter of 2015. Module shipments recognized in revenue totaled 1,161 MW, compared to 1,290 MW recognized in revenue in the second quarter of 2016 and 1,150 MW recognized in revenue in the third quarter of 2015. Solar module shipments recognized in revenue in the third quarter of 2016 included 16.3 MW used in the total solutions business, compared to 18.7 MW in the second quarter of 2016 and 110.5 MW in the third quarter of 2015.

The following table is a summary of net revenues by geographic region based on the location of customers’ headquarters (in millions of US$, except percentages).

Q3 2016

Q2 2016

Q3 2015

$

% $ % $

%

The Americas $270.2 41.1 $383.9 47.6 $447.0 52.6
Asia 280.6 42.7 318.4 39.5 351.1 41.3
Europe and Others 106.5 16.2 103.6 12.9 51.7 6.1
Total $657.3 100.0 $805.9 100.0 $849.8 100.0

Gross profit in the third quarter of 2016 was $117.3 million, compared to $138.5 million in the second quarter of 2016 and $126.8 millionin the third quarter of 2015. Gross margin in the third quarter of 2016 was 17.8%, compared to 17.2% in the second quarter of 2016 and 14.9% in the third quarter of 2015. The sequential increase in gross margin was primarily due to lower module costs resulting from decreased purchase price of wafer and cell as well as improved manufacturing efficiency of the Company.

Total operating expenses were $90.3 million in the third quarter of 2016, down 8.7% from $98.9 million in the second quarter of 2016 and 5.9% from $95.9 million in the third quarter of 2015.

Selling expenses were $34.0 million in the third quarter of 2016, up 0.3% from $33.9 million in the second quarter of 2016 and down 8.8% from $37.2 million in the third quarter of 2015. The slight sequential increase in selling expenses was primarily due to higher labor costs, partially offset by lower shipping and handling expenses and external sales commission. The year-over-year decrease in selling expenses was primarily due to lower external sales commission, partially offset by higher labor costs.

General and administrative expenses were $51.7 million in the third quarter of 2016, down 13.8% from $60.0 million in the second quarter of 2016 and 5.4% from $54.6 million in the third quarter of 2015. Excluding the non-recurring charges recorded in the second quarter, which include a $10.8 million charge for the terminated YieldCo launch and a $7.6 million estimated tornado damage to the Company’s Funing cell factory, and a $20.8 million expense recorded in the third quarter of 2015 for the settlement of LDK arbitration case, general and administrative expenses actually increased sequentially and year-over-year primarily due to an approximately $6.6 million impairment charge for certain solar power systems as well as higher labor costs.

Research and development expenses were $4.6 million in the third quarter of 2016, compared to $5.1 million in the second quarter of 2016 and $4.1 million in the third quarter of 2015.

Income from operations was $27.0 million in the third quarter of 2016, compared to $39.6 million in the second quarter of 2016, and $30.9 million in the third quarter of 2015. Operating margin was 4.1% in the third quarter of 2016, compared to 4.9% in the second quarter of 2016 and 3.6% in the third quarter of 2015.

Non-cash depreciation and amortization charges were approximately $25.4 million in the third quarter of 2016, compared to $25.5 million in the second quarter of 2016, and $24.8 million in the third quarter of 2015. Non-cash equity compensation expense was $1.8 million in the third quarter of 2016, compared to $1.9 million in the second quarter of 2016, and $1.4 million in the third quarter of 2015.

Interest expense was $18.8 million in the third quarter of 2016, compared to $11.9 million in the second quarter of 2016, and $13.0 million in the third quarter of 2015. The increase in interest expense was mainly due to lower capitalized interest, a higher balance of outstanding debt and higher financing costs for the Company’s projects in the U.S.

Interest income was $2.1 million in the third quarter of 2016, compared to $2.4 million in the second quarter of 2016 and $4.2 million in the third quarter of 2015.

The Company recorded a gain on change in fair value of derivatives of $2.0 million in the third quarter of 2016, compared to a loss on change in fair value of derivatives of $1.6 million in the second quarter of 2016 and a loss on change in fair value of derivatives of $12.3 million in the third quarter of 2015. The gain on change in fair value of derivatives in the third quarter of 2016 came primarily from the change in fair value of warrants of $1.7 million.

The Company recorded a foreign exchange gain in the third quarter of 2016 of $4.4 million compared to a gain of $24.9 million in the second quarter of 2016 and a gain of $17.1 million in the third quarter of 2015.

Income tax expense was $16 thousand in the third quarter of 2016, compared to $16.3 million in the second quarter of 2016 and income tax benefit of $3.9 million in the third quarter of 2015.

Net income attributable to Canadian Solar was $15.6 million, or $0.27 per diluted share, in the third quarter of 2016, compared to net income of $40.4 million, or $0.68 per diluted share, in the second quarter of 2016, and net income of $30.4 million, or $0.53 per diluted share, in the third quarter of 2015.

Financial Condition

The Company had $986.0 million of cash, cash equivalents and restricted cash as of September 30, 2016, compared to $1.0 billion as of June 30, 2016. As of the end of the third quarter of 2016, $24.7 million of cash, cash equivalents and restricted cash, among other assets, was reclassified under ‘Assets held-for-sale’ as further discussed below.

Accounts receivable, net of allowance for doubtful accounts, at the end of the third quarter of 2016 were $350.1 million, compared to $356.7 million at the end of the second quarter of 2016. As of the end of the third quarter of 2016, $18.7 million of accounts receivable was reclassified to ‘Assets held-for-sale’ as further discussed below. Accounts receivable turnover was 68 days in the third quarter of 2016, compared to 60 days in the second quarter of 2016.

Inventories at the end of the third quarter of 2016 were $313.9 million, compared to $309.7 million at the end of the second quarter of 2016. Inventory turnover was 56 days in the third quarter of 2016, compared to 51 days in the second quarter of 2016.

As of September 30, 2016, the Company had $436.0 million of solar power system assets carried as non-current assets, compared to $1.8 billion at the end of the second quarter of 2016. These assets included operating solar plants as well as plants under construction, which the Company held for the purpose of generating electricity income. In the third quarter, the Company has decided to sell certain solar power plants and as a result it has reclassified $1.6 billion of assets under these projects legal entities, including $1.5 billion of solar power systems, $24.7 million of cash, cash equivalents and restricted cash and $18.7 million of accounts receivable, to ‘Project assets – current’ and ‘Assets held-for-sale’. Total project assets and assets held-for-sale at the end of the third quarter of 2016 were $1.2 billion and $529.2 million respectively. Correspondingly, the Company also reclassified $356.3 million of liabilities, primarily including $143.5 million of short-term borrowings and $151.7 million of long-term borrowings associated with these assets held-for-sale, to ‘Liabilities held-for-sale’.

Accounts and notes payable at the end of the third quarter of 2016 were $801.9 million, compared to $937.3 million at the end of the second quarter of 2016.

Short-term borrowings at the end of the third quarter of 2016 were $1.51 billion, compared to $1.37 billion at the end of the second quarter of 2016. Long-term debt at the end of the third quarter of 2016 was $615.8 million, compared to $828.5 million at the end of the second quarter of 2016. Senior convertible notes totaled $125.4 million at the end of the third quarter of 2016, compared to $128.0 million at the end of the second quarter of 2016. Short-term borrowings and long-term debt directly related to utility-scale solar power projects totaled $1.18 billion at the end of the third quarter of 2016, compared to $834.9 million at the end of the second quarter of 2016.

Dr. Shawn Qu, Chairman and Chief Executive Officer of Canadian Solar, remarked: “Our solar module shipments and revenue came in at the low end of our guidance, due to the dislocation of the global solar market during the quarter and the quarter-end logistic disruption caused by the bankruptcy of Hanjin Shipping in September. Our team has effectively managed the supply chain and our own production output to offset the macro impact of solar module ASP declines in the broader market. We achieved a gross margin of 17.8%, which was well above our guidance and reflects our strong inventory management and continued improvement in manufacturing efficiencies. During the quarter, we continued to develop our downstream energy business. At the end of the quarter, our late-stage solar project pipeline stood at 2.0 GWp and our portfolio of solar plants in operation totaled 948 MWp. Our footprint now covers the world’s most attractive markets: the U.S., Canada, Japan, Brazil, China, Mexico, the United Kingdom and Africa. Investor interest in our high-quality project pipeline remains robust. We target to complete the sale of certain solar power plants in Canada and China either by the end of 2016 or early next year and have started the sales process of our projects in the U.S. as our projects there reaching COD. This follows our sale of 80% of the equity in our 191.5 MWp Pirapora 1 solar power project in Brazil to EDF EN do Brasil, the local subsidiary of EDF Energies Nouvelles. Developing and transferring will be an important strategy in our downstream energy business as it bolsters our balance sheet, reduces market risk, and allows us to redeploy our capital, while providing an attractive return for our shareholders.”

Dr. Huifeng Chang, Senior Vice President and Chief Financial Officer of Canadian Solar, added: “Our results for the third quarter reflect our disciplined business strategy and successful execution. Declines in wafer and cell ASPs, together with improved management in inventory control and manufacturing efficiencies, helped offset the impact of further module ASP declines. We continue to strengthen our capacity profile with selective investments in new wafer, cell and module plants. The work to restore our Funing cell factory is proceeding on schedule. We expect to have the first two of our ten production lines up and running by the end of 2016, and remaining production lines back in full production by the end of the first half of 2017. We continue to discuss the amount of our total damages claim with our insurers and have received prepayments totaling RMB120 million from the insurer. Importantly, all of the equipment we are installing features the latest production technologies.”

Utility-Scale Solar Project Pipeline

The Company divides its utility-scale solar project pipeline into two parts: an early- to mid-stage pipeline and a late-stage pipeline. The late-stage pipeline includes primarily projects that have energy off-take agreements and are expected to be built within the next two to four years. The Company cautions that some late-stage projects may not reach completion due to risks such as failure to secure permits and grid connection, among other risk factors.

Late-Stage Utility-Scale Solar Project Pipeline

As of September 30, 2016, the Company’s late-stage pipeline totaled 2.0 GWp of utility-scale solar project pipeline, which included 940 MWp in the U.S., 597 MWp in Japan, 390 MWp in Brazil, 38 MWp in China, 63 MWp in Mexico, 15 MWp in the United Kingdom and 6 MWp in Africa.

In the United States, as previously announced, three projects (Barren Ridge, Mustang and Tranquillity) totaling 470 MWp reached commercial operation in the third quarter of 2016. Four other projects (Astoria 1, Astoria 2, Garland and Roserock) are currently under construction and are expected to reach commercial operation before the end of December 2016. In September 2016, the Company announced the signing of a 15-year power purchase agreement (“PPA”) for 100 MWac, or 140 MWp, of its solar power project Tranquility 8 in California with MCE, California’s first operating Community Choice Aggregation program. Construction of the project is expected to begin in 2017. The project will begin providing power to MCE by late 2018. The Company’s late-stage utility-scale solar project pipeline in the U.S. as of September 30, 2016 is detailed in the table below.

Project Gross MWp Location Status Expected COD
Astoria 1 131 CA Construction 2016
Astoria 2 100 CA Construction 2016
Garland 272 CA Construction 2016
Roserock 212 TX Construction 2016
Tranquility 8 197 CA Development 2018
Project B 28 CA Development 2018
Total 940

In Japan, during the third quarter of 2016, the Company started commercial operation of two solar power plants, with a total capacity of approximately 1 MWp. In November, a 24 MWp solar power plant started commercial operation. As of September 30, 2016, the Company’s pipeline of late-stage utility-scale solar power projects totaled approximately 597 MWp with 191 MWp in construction and 66 MWp at the ready-to-build stage. As of September 30, 2016, the expected commercial operation schedule of the Company’s late­-stage utility-­scale solar power projects in Japan is detailed in the table below.

Expected COD Schedule (MWp)
2016 2017 2018 2019 2020 2021 and Thereafter Total
41 121 157 77 126 75 597

 

As of August 1, 2016, Canadian Solar had executed interconnection agreements for 397 MWp of projects. The Company expects that, by April 1, 2017, it will have executed interconnection agreements for an additional 130 MWp of projects, thereby securing the existing FIT contract subject to meeting the COD deadline. The Company is working to advance an additional 92 MWp of projects, so that the interconnection agreements can be executed by April 1, 2017 in order to secure the existing FIT contract.

In Brazil, the Company’s late-stage, utility-scale solar project pipeline as of September 30, 2016 is detailed in the table below.

Project Gross MWp Location Status Expected COD
Pirapora I 191 Brazil Construction 2017
Pirapora II 109 Brazil Development 2018
Vazante 90 Brazil Development 2018
Total 390

 

In October 2016, as previously announced, Canadian Solar sold 80% of equity interest in its Pirapora I solar project in Brazil to EDF EN do Brasil, the local subsidiary of EDF Energies Nouvelles. Canadian Solar will supply modules for this project from its new 360 MWp module factory established in Brazil to support the local market.

In addition, during the third quarter of 2016, the Company connected a 5 MWp plant in the UK to the grid.

Solar Power Plants in Operation

In addition to its utility-­scale solar project pipeline, the Company had a portfolio of solar power plants in operation totaling approximately 948 MWp as of September 30, 2016. Revenue from the sale of electricity generated by these plants in the third quarter of 2016 totaled $24.1 million, compared to $22.5 million in the second quarter of 2016. The resale value of these plants is estimated at approximately $1.4 billion, with an expected total profit margin contribution in low double digits. The Company cautions, however, that market conditions may change resulting in different sale values if and when the Company ultimately sells these plants. The sale of projects recorded on the balance sheet as ‘Project assets’ (build­-to-­sell) will be recorded as revenue once revenue recognition criteria are met, and the gain from sale of projects recorded on the balance sheet as ‘Assets held-for-sale’ and ‘Solar power systems, net’ (build­-to-­own) will be recorded within ‘Other income (expenses)’ in the income statement.

Plants in Operation (MWp)

U.S. Canada Japan U.K. China Other Total
483 100 22 120 218 5 948

 

Manufacturing Capacity

During the third quarter of 2016, the Company adjusted its end of 2016 manufacturing capacity, as summarized in the table below.

Manufacturing Capacity Roadmap (MW)
December 31, 2015 June 30, 2016 December 31, 2016
Wafer 400 400 1,000
Cell 2,700 2,200 2,440
Module 4,330 4,330 5,800

The Company’s wafer manufacturing capacity has reached 1.0 GW, including 400 MW using slurry wire-saw and 600 MW using the new diamond wire-saw technology. The Company expects its wafer capacity to reach 1.3 GW by April 2017, all of which will use the diamond wire-saw technology. This is slightly behind the Company’s previous schedule as the production capacity of the diamond wire-saw has to match with that of the black silicon surface treatment in the solar cell workshop. The diamond wire-saw technology works compatibly with the Company’s proprietary and highly efficient Onyx black silicon multi-crystalline solar cell technology, reducing silicon usage and therefore manufacturing cost.

The Company’s cell manufacturing capacity as of the end of 2016 is expected to reach 2.4 GW, as compared to the 3.1 GW prior target. The decrease is primarily due to a delay in the construction of the Company’s new 850 MW cell plant in Southeast Asia. While the module plant in the same compound went on line on schedule in September, the construction completion date of the solar cell plant has been extended to the first quarter of 2017. The decrease in the cell capacity will be partially offset by an earlier than expected partial resumption in production at the Company’s Funing cell factory, which was damaged by a tornado in June 2016.

The Company continues to expect that its internal module capacity will reach 5.8 GW by the end of 2016.

Business Outlook

The Company’s business outlook is based on management’s current views and estimates with respect to operating and market conditions, its current order book and the global financing environment. It is also subject to uncertainty relating to customer final demand and solar project construction schedule. Management’s views and estimates are subject to change without notice.

For the fourth quarter of 2016, the Company expects total solar module shipments to be in the range of approximately 1.4 GW to 1.5 GW, including approximately 30 MW of shipments to the Company’s utility-scale solar power projects that may not be recognized as revenue in fourth quarter 2016. Total revenue for the fourth quarter of 2016 is expected to be in the range of $600 million to $750 million. Gross margin for the fourth quarter is expected to be between 11% and 16%.

The recent demand for the Company’s solar module products has been very strong. The shipment volume in the fourth quarter is impacted by the availability of the Company’s solar module manufacturing capacities. The Company is overbooked for the current quarter and fully booked for the first quarter of 2017. As a result, the Company has to use third party solar modules for some of its own projects, in order to satisfy the demand from its solar module customers. The gross margin in the quarter is impacted by the loss-of-service of the company’s 1 GW solar cell factory in Funning damaged by a tornado in June and the delay in construction of the company’s 850 MW new cell factory in Southeast Asia. The company expects to bring the Funning cell factory partially back in service at the end of the year and fully back in service by June 2017. Meanwhile, the Company expects to start production on its new cell factory in Southeast Asia in the first quarter of 2017.

The Company expects to complete the sale of certain utility-scale solar power plants in Canada and China either in the fourth quarter of 2016 or early 2017. The total value of these solar power plants is estimated at approximately $500 million with a blended gross margin in high teens. According to US GAAP, the Company expects to recognize approximately $150 million of the proceeds of these sales as revenue. The remaining proceeds, net of the book value of the projects, estimated at $50 million to $55 million, will be recognized as gain from sale of projects under ‘Other income (expenses)’ in the income statement. The actual figures may be different, subject to the adjustments at the final closing. The Company expects to reach the high end of its revenue and gross margin guidance if all these solar power plant sales are completed in the fourth quarter, or the low end of the revenue and gross margin guidance if all these projects sales are closed in 2017 instead.

Accordingly, for the full year 2016, the Company expects its guidance for total module shipments to be in the range of approximately 5.073 GW to 5.173 GW, compared to 5.4 GW to 5.5 GW as previously guided. Management expects its revenue under US GAAP for the full year 2016 to be in the range of $2.78 billion to $2.94 billion, compared to $3.0 billion to $3.2 billion as previously expected. The updated revenue guidance is based on US GAAP, therefore, does not contain the sales of approximately $300 million of solar power plant assets, which may occur in the fourth quarter or early 2017, as previously discussed.

Dr. Shawn Qu, Chairman and Chief Executive Officer of Canadian Solar, remarked: “We remain confident in our long-term outlook and in our proven ability to navigate through disruptive, lower-visibility market environments. Canadian Solar has always emerged in a stronger position from these periods of market volatility. We will continue to invest in advanced technologies that will deliver even higher module efficiency. We expect to further benefit from our global brand and flexible capacity structure. Our track record of stability and consistent long-term execution sets Canadian Solar apart from our peers. Our financial partners share our confidence and positive outlook for the global solar industry. Our bankability is further underscored by our recent issuance of total RMB900 million commercial papers and entry into a JPY9.6 billion 3-year loan facility.”

Recent Developments

On November 17, 2016, Canadian Solar announced that it has started the commercial operation of a 24 MWp solar power plant in Yamaguchi Prefecture, Japan. The plant is expected to generate approximately 28,487 MWh of electricity each year, which will be purchased by Chugoku Electric Power Company, under a 20-year feed-in-tariff contract at the rate of JPY40.00 (US$0.38) per kWh.

On October 13, 2016, Canadian Solar announced that it had entered into a syndicated 3-year loan facility for JPY9.6 billion (US$95 million) with Sumitomo Mitsui Banking Corporation as the lead arranger. The loan proceeds will be used to finance solar project development in Japan and for general corporate working capital requirements.

On October 11, 2016, Canadian Solar and EDF Energies Nouvelles announced the sale of 80% interest in Canadian Solar’s 191.5 MWp Pirapora I solar energy project in Brazil to EDF Energies Nouvelles’ local subsidiary, EDF EN do Brasil. The project has started construction and is expected reach commercial operation in the third quarter of 2017. Canadian Solar will supply the modules for the project from its new 360 MWp modules factory established in Brazil to support the local market.

On September 29, 2016, Canadian Solar announced the start of commercial operation of the 60 MWac/78 MWp Barren Ridge solar photovoltaic project developed by the Company’s wholly owned subsidiary, Recurrent Energy. The Barren Ridge solar project, also known as the RE Cinco Project, supplies electricity and associated renewable energy credits to the Los Angeles Department of Water and Power under a long-term power purchase agreement.

On September 28, 2016, Canadian Solar announced that it was awarded US$3.5 million funding from Australian Renewable Energy Agency for two solar power projects, totaling 47MWp in Australia. The Company plans to start the construction of both projects in the first quarter of 2017 and achieve commercial operations no later than January 2018.

On September 27, 2016, Canadian Solar announced that its wholly-owned subsidiary, Recurrent Energy, entered into a 15-year PPA for 100 MWac of solar power in California with MCE, California’s first operating Community Choice Aggregation program. Construction of the project is expected to begin in 2017 and the project will begin providing power to MCE by late 2018.

On September 26, 2016, Canadian Solar announced the start of commercial operation of the 200 MWac/258 MWp Tranquility solar power project in California. The Tranquility solar power project was developed by the Company’s wholly owned subsidiary, Recurrent Energy, and is majority-owned by Southern Company subsidiary Southern Power.

On September 21, 2016, Canadian Solar announced that it signed a financing agreement pursuant to which Export Development Canada has agreed to provide guarantees or letters of credit of up to US$100 million to Canadian Solar to support its global activities of project development. Royal Bank of Canada and Toronto Branch of China Construction Bank Corporation will serve as fronting banks on the facility.

In September 2016, Canadian Solar issued a RMB400 million (US$60 million) commercial paper with a fixed interest rate of 5.5% and a tenor of one year and a RMB500 million (US$74.8 million) commercial paper for a term of 9 months with a fixed interest rate of 5.3%. The Company intends to use the proceeds from these issuances to repay debt and to enhance its working capital. China CITIC Bank Corporation Limited acted as the underwriter and bookrunner of the issuance.

On August 23, 2016, Canadian Solar announced that its wholly owned subsidiary, Recurrent Energy, reached commercial operation of the 100 MWac/134 MWp Mustang solar power project in Kings County, California.

 

Source : PR Newswire