JSW Energy Limited today reported its results for the quarter ("Q2 FY25" or the "Quarter") ended September 30, 2024.
Key Highlights of Q2 FY25
Operational:
- Net Generation increased 14% YoY at 9.8 BUs driven by wind capacity additions, higher generation at thermal and hydro plants
- Total RE generation is up by 14% YoY at 5.0 BUs driven by 37% YoY increase in wind generation and 5% YoY increase in hydro generation; Total thermal generation is up by 14% YoY at 4.8 BUs
- Long Term PPA Generation: Up by 9% YoY
Consolidated Financials:
- Reported EBITDA declined by 5% YoY to , 1,907 Cr while underlying EBITDA increased 4% YoY primarily on account of higher generation
- PAT and Cash PAT were marginally up YoY at ,853 Cr and ,1,190 Cr, respectively
- Best in class Balance Sheet: Net Debt to Equity at 0.9x, Net Debt to EBITDA1 at 4.lx, Net Debt to EBITDA1 {excl. CWIP) at 2.2x
- Receivables on DSO basis stood at 70 days
- Cash & Cash Equivalents2 stood at, 5,719 Cr
ESG and Sustainability
- MSCI: Achieved an 'A' rating from MSCI for ESG practices
- CDP: Climate A- (Leadership) I Water Security B {Management)
- DJSI: Achieved highest ever score of 77 /100 in S&P Global DJSI - ESG rating
- GPTW: Recognised as 'Best Workplaces' by 'Great Place to Work' in 2024
Growth Projects:
Generation: Total locked-in capacity of 19.2 GW
- 204 MW of wind capacity commissioned during the quarter; 495 MW of capacity added in YTD FY25 resulting in total installed capacity of 7.8 GW
- Commissioning of 440 MW of 454 MW SECI X Wind Project
- Won RE bids to install 3.7 GW taking the total locked-in generation capacity to 19.2 GW
- New PPAs signed for 3.8 GW of RE projects during the quarter, with this 2/3rd of the projects won in CY24 have been tied-up under long-term PPA
Products and Services
- Green Hydrogen: Equipment deliveries started and civil works in progress for the 3,800 TPA hydrogen supply agreement with JSW Steel; expected commissioning by Mar-25
- BESS: Construction of the 1.0 GWh SECI project is in progress with expected commissioning by Jun-25
- Pumped Hydro Storage: Signed Energy Storage Facility Agreement for 12 GWh of Pumped Hydro Storage with Maharashtra State Electricity Distribution Company, expected commissioning in 48 months.