ISTS Waiver Sunset Casts Shadow On 26 GW Renewable Projects: Crisil

Transmission costs, which vary by project type, location, and usage, typically range from Rs 0.5 to Rs 1.5/kWh, and the reduction in waivers is expected to moderate long-term project cash flow, affecting project returns.

author-image
Chitrika Grover
transmission

ISTS Waiver Sunset Casts Shadow On 26 GW Renewable Projects: Crisil

India currently has around 26 Gigawatt (GW) of utility-scale renewable energy projects under construction, for which power purchase agreements (PPAs) have already been signed. Sharing this insight, the recent CRISIL report forecasts a moderation in cash flow in these projects following the expiry of the 100% inter-state transmission system (ISTS) charge exemption on June 30, 2025.   

Advertisment

The research has attributed the delay in project commissioning to procedural, regulatory, and infrastructure-related challenges, which it suggests may now be subject to a phased reduction in benefits.

Govt Regulation on ISTS charge waiver

CRISIL research also found that the ISTS charge waiver, introduced by the Ministry of Power (MoP) in 2016 and subsequently extended, was initially important in encouraging renewable energy development by exempting eligible projects from ISTS charges. It enabled solar and wind-rich states like Rajasthan and Gujarat to supply power cost-effectively to demand centres across India. However, the incentive always had a sunset date.  As part of a scheduled phase-down, only projects commissioned by June 30, 2025, would continue to enjoy the full exemption for 25 years. 

Impact of ISTS Charges

The CRISIL study also mentioned that projects that are covered under the waiver policy but missed this deadline would be eligible for partial concessions: 75% waiver for those completed by June 2026, 50% for those completed by June 2027, and 25% for those completed by June 2028, after which the waiver will be fully discontinued. And, although ISTS charges are typically borne by the offtaker, developers for these capacities may be liable if delays are deemed solely attributable to them.

Impact On Transmission Cost

Advertisment

Transmission costs, which vary by project type, location, and usage, typically range from Rs 0.5 to Rs 1.5 per kilowatt-hour (kWh).The reduction in waivers is expected to moderate long-term project cash flow, potentially affecting the debt service coverage ratio (DSCR) and project returns.

For instance, if a developer bears 25% of an assumed Rs 0.65/kWh transmission charge due to the waiver sunset, we may see DSCR decline from 1.4 times to 1.3 times 

Transmission charges applicable on developer

CRISIL Analysis

Advertisment

Considering, around three-fourths of the affected capacity is expected to be commissioned by June 2026 and will still qualify for a 75% waiver, large-scale sectoral impact and material downside in returns from the phase-down is expected to be limited. Additionally, most of these under-construction projects are backed by established developers, which provides financial flexibility. That said, if any project is impacted, they may see their project returns moderate by 80 to 370 basis points, depending on project type, bid competitiveness, and date of commissioning," says Ankit Hakhu, Director, Crisil Ratings. 

The study further estimated that the delayed projects under analysis may still be able to claim full exemption if the delays are due to certain circumstances.

Mohini Chatterjee, Team Leader, Crisil Ratings, said, “The circular allows for extension of waiver for any force majeure event, including the non-availability of transmission infrastructure, or for any other delay not attributable to the developer. However, approvals will be contingent on the decision of the concerned regulator. Considering these will be evaluated on a case-by-case basis, timely and satisfactory resolution of waiver-related disputes will be critical for the standalone credit profiles of these projects.”

All said, the government continues to support the overall renewables industry, with a sharpening focus on grid stability, having extended the full ISTS charge exemption for battery energy storage systems and pumped hydro projects until June 2028.