/saur-energy/media/media_files/2025/08/26/solar-energy-manufacturing-2025-08-26-10-48-34.jpg)
Insolation Green Energy, a subsidiary of Jaipur-based Insolation Energy, shared a business update covering its board migration status and the solar module, cell, and aluminium order book secured by the company.
In a regulatory filing, it also announced the commencement of commercial operations at its new 3 GW PV module manufacturing lines in Sawarda, Jaipur. The company said it plans to commission the remaining 1.5 GW by January 2026.
In addition to the project update, Insolation Energy mentioned that it has secured BIS certification for G12R panels up to 635 Wp, adding that ALMM approval is expected to follow soon.
Insolation Makes Progress On 4.5 GW Solar Cell Plant
The company shared an update on its 4.5 GW solar cell manufacturing project and its 18,000 MT aluminium frame manufacturing plant at Narmadapuram, Madhya Pradesh. It said that civil and PEB construction work is underway at full pace at its 4.5 GW TOPCon G12R solar cell manufacturing facility.
Insolation energy also placed a major plant equipment order, and said that advances have been released. Utility design packages are in the final stages of discussion, and long-lead items are being ordered to keep the project on schedule.
Advancing Aluminium Frame Manufacturing
Providing the status of its 18,000 MT aluminium frame manufacturing plant, Insolation Energy said construction work is progressing. Civil and PEB construction has begun, and foundations for the main plant are being laid. The company has also placed major plant and machinery orders and released advances.
Insolation Energy currently has an order book that includes 1,750 MW of solar module supply orders and 625 MW of EPC project orders.